Elazığ solar energy plant, will be installed on 60.000 m2 area at Yemişlik district. The total capacity of the power plant is 7.410 kWp. After installation and commissioning, Elazıg SPP will produce totally 10,181,243 kWh of electricity annually. Elazığ SPP will save 18.226 trees and prevent the release of 7.356 tons of CO2. The grid connection is expected on 2017.
Location | Elazığ |
Assembly Type | Ground Mounted Solar Power Systems |
Field (m2) | 60.000 m2 |
Situated Power | 7.410 |
Yearly Expected Production Amount ( kWh) | 10.181.243,82 |
Blocked CO2 Amount ( tonne) | 7.356,00 |
Recovered Tree Amount(unit) | 18.226 |
PV Module Brand and Power | Trina Policristalin 265 Wp |
PV Module Amount | 27.962 |
Inverter Brand | ABB Trio 50 |
Inverter Amount | 136 |
Construction Duration | 5 Monty |
Activation Date | 2017 |