Kayseri BCKK GES located in Kayseri has a total capacity of 6.317 kWp with an estimated annual energy production of roughy 10.075.615 kWh, avoiding the emission of over 6.103 tons of CO2 per year and saving 14.800 trees per year. Plant will be installed on the area of 115000m2.

The construction of the solar farm was started at the beginning of 2016. The grid connection is expected on 2016.
Location  Kayseri
Assembly Type  Zemin
Field (m2) 115000
Situated Power 6317
Yearly Expected Production Amount ( kWh)  10.075.615
Blocked CO2 Amount ( tonne)  6103
Recovered Tree Amount(unit)  14800
PV Module Brand and Power Trina Solar PD05-60 All Max
PV Module Amount  24288
Inverter Brand ABB Trio 27,6 kW
Inverter Amount  184
Construction Duration  7 ay
Activation Date 2016

 

Facebook
Google+
http://teknoraysolar.com.tr/en/kayseri-bckk-ground-mounted-project
YouTube
LinkedIn
For more information

You can get in touch by calling



Follow us on Social Media!

Subscribe to new updates!

We will let you know about the latest news!


I want to sign up



İLETİŞİME GEÇİN

X
İLETİŞİME GEÇİN